Materials Cost per Square Foot for Epoxy Floors: A Contractor's Estimating Sheet
Materials for a finished epoxy floor run $1.77 to $2.01 per sq ft for a solid-color Garage Pro System and $2.75 to $2.96 for full flake, with topcoat and tools in the price. A commercial floor is $1.32 to $1.42 per sq ft solid or $2.69 to $2.74 flake. Those numbers are the kit price divided by the rated coverage at the recommended thickness; the worksheet below adds prep, repairs, primer, waste and labor. Prices as of November 2026; contractor pricing is by phone.
Materials per square foot by system and finish
| System and finish | 1 bay, up to 350 sq ft | 2 bays, up to 700 | 3 bays, up to 1,050 | 4 bays, up to 1,400 | What is in it |
|---|---|---|---|---|---|
| Garage Starter, solid color | $350.99 ($1.00/sq ft) | $665.99 ($0.95) | $980.99 ($0.93) | $1,295.99 ($0.93) | B-707 at about 14 mils, mix wand, notched squeegee. No topcoat |
| Garage Pro, solid color | $702.99 ($2.01) | $1,270.99 ($1.82) | $1,862.99 ($1.77) | $2,541.99 ($1.82) | B-707, T-521 gloss, tool kit |
| Garage Pro, full flake | $1,036.99 ($2.96) | $1,961.99 ($2.80) | $2,887.99 ($2.75) | $3,923.99 ($2.80) | B-707, 40 lb flake per bay, T-444X, tool kit |
| Garage Pro, metallic | $1,005.99 ($2.87) | $1,875.99 ($2.68) | $2,769.99 ($2.64) | $3,751.99 ($2.68) | P-015 black, C-671 with pigment at 16 to 18 mils, T-521, tool kit |
| Garage One-Day, full flake | $910.99 ($2.60) | $1,709.99 ($2.44) | $2,509.99 ($2.39) | $3,419.99 ($2.44) | B-933 polyurea, flake, T-444X, tool kit |
| Garage One-Day, solid color | $854.99 ($2.44) | $1,598.99 ($2.28) | $2,341.99 ($2.23) | $3,196.99 ($2.28) | Two coats T-444X, first tinted, tool kit |
| Basement & Indoor Pro, solid color | $820.99 ($2.35) | $1,501.99 ($2.15) | $2,210.99 ($2.11) | $3,002.99 ($2.14) | B-707, T-520 matte, tool kit. Flake matches Garage Pro flake |
Every kit price in this table was checked against the live store on November 10, 2026.
| Commercial Pro | Up to 2,000 sq ft | Up to 5,000 sq ft | What is in it |
|---|---|---|---|
| Solid color | $2,831.99 ($1.42) | $6,614.99 ($1.32) | B-707 at about 14 mils, T-322 solvent urethane, tool kit |
| Full flake | $5,487.99 ($2.74) | $13,462.99 ($2.69) | B-707, flake, T-444X, tool kit |
The commercial numbers and installed-price discussion are in commercial epoxy flooring cost per square foot. Homeowner pricing with installer ranges is in how much it costs to epoxy a garage floor.
Materials per square foot by component
For a crew buying components instead of kits, at rated coverage on a profiled slab:
| Component | Kit and price | Coverage | Per sq ft |
|---|---|---|---|
| B-707 High Build Epoxy, base at 14 mils | 3 gal $349.99; 15 gal $1,606.99 | 350; 1,750 sq ft | $1.00; $0.92 |
| B-933 Fast Cure Polyurea, base under flake | 2.5 gal $209.99 | one bay | $0.60 |
| P-707LVP primer, when specified | 3 gal $269.99 | about 600 sq ft | $0.45 |
| T-521 over smooth, 3 to 5 mils wet | 1.5 gal $306.99; 3 gal $587.99 | one bay; two bays | $0.88; $0.84 |
| T-444X over flake, 5 to 12 mils wet | 2 gal $387.99; 10 gal $1,887.99 | one bay; five bays | $1.11; $1.08 |
| T-322 over smooth | clear, 1.5 gal $224.99; 15 gal $2,059.99 | one bay; about 6,000 sq ft | $0.64; $0.34 |
| T-359, rolled thin | 1 gal kit $249.99 | about 600 sq ft | $0.42 |
| Flake, 1/4 inch, full broadcast | 40 lb box $289.99 | one bay | $0.83 |
| A-HWS anti-slip | pint $29.99 | one 1.5 gal topcoat kit | $0.09 |
| Application tool kit | $123.99 | one job |
The kits price below the sum of their components. Component math for odd floor sizes: how much epoxy do I need.
The estimating worksheet
- Coating system. Kit price from the table, or components. Round the floor up to the kit size; a 760 sq ft floor is a 3-bay kit.
- Waste. Add 10% to component quantities as a working rule. Kit sizes already carry margin to the top of their range.
- Prep. Grinder rental by the day with diamond cups and a HEPA vacuum. Our working figures: about $150 per day for a single-head grinder, a few hundred dollars a day for a walk-behind planetary grinder with a dust extractor, and a 5,000 sq ft slab is a two-day grind for two people. Rental rates vary by market, so price it at your local counter. Add degreaser, tape and plastic sheeting.
- Crack repair. R-818 Epoxy Crack Filler covers about 1,228 lineal ft of 1/8 by 1/8 inch crack per gallon; the 1 gal kit at $99.99 handles a typical 2-car garage, about $0.14 per sq ft over 700 sq ft. Heavily cracked slabs: the 2 gal kit at $154.99.
- Spalls and joints. R-343 Concrete Quick Fix small kit $49.99 for a handful of spalls, large kit $69.99 for a dozen or a broken slab edge. R-830 Flexible Joint Sealant at $59.99 per tube set covers 11 to 12 lineal ft; a 2-car garage with two control joints takes 4 tube sets, $239.96. Forklift lanes and dock edges: R-110 Epoxy Mortar at $174.99 per unit, 21.5 sq ft at 1/4 inch.
- Primer, when needed. On ground concrete that passed the moisture test, none. Slab failed the plastic-sheet test: P-409 Moisture Vapor Primer at 94 sq ft per gal and 17 mils, $389.99 per 3 gal kit (about 280 sq ft, $1.39 per sq ft) or $1,719.99 per 15 gal kit (about 1,400 sq ft, $1.23 per sq ft). It is the most expensive line after the coating itself. Oil in the slab: P-820 Oil Stop Primer, 2 gal $159.99 for 400 to 640 sq ft of stains, about $0.25 to $0.40 per sq ft spot-primed; P-820 cannot ship to CA, CO, CT, DE, MD, MI, NY, OH, RI or UT.
- Labor. Price your own crew hours in four blocks per bay: grind, repair and vacuum; mix, pour, squeegee and back-roll the base coat; broadcast flake; scrape, vacuum and roll the topcoat. A two-person crew finishes a residential flake floor in two working days. Recoat and cure times: recoat windows and cure times chart.
Example: 2-car garage, 440 sq ft, full flake, slab passes moisture test
- Garage Pro full flake, 2-bay kit: $1,961.99
- Grinder rental for one day: about $150, plus diamond cup wear
- R-818 1 gal kit: $99.99
- R-830, 4 tube sets for two joints: $239.96
- Materials and prep: about $2,450, or $5.57 per sq ft of actual floor
- Labor: two people, two days, plus a return visit to inspect
If the slab fails the moisture test, add two 3 gal kits of P-409 at $779.98, which moves the floor to about $7.35 per sq ft in materials and prep.
Recoats and old coatings
Every topcoat here goes over B-707 inside its recoat window, 8 to 12 hr and within 48 hr; after 48 hr price a full screen and vacuum. Epoxy over a cured polyaspartic or urethane, or over an unknown old coating, needs a screen, an adhesion test patch and a call to us first, so price the screening. Which topcoat goes where: which topcoat goes over your epoxy floor.
Common questions
How much does epoxy garage floor cost per square foot in materials?
$1.77 to $2.01 per sq ft for the solid-color Garage Pro System, $2.75 to $2.96 for full flake, $0.93 to $1.00 for the Starter base coat alone. Prep, repairs and primer are extra.
How much does commercial epoxy flooring cost per square foot?
$1.32 to $1.42 per sq ft in materials for the solid-color Commercial Pro System, $2.69 to $2.74 for full flake, before primer, repairs and labor.
What should a contractor add on top of the kit price?
Grinder, cups and vacuum; crack filler at about $0.14 per sq ft; moisture primer at $1.23 to $1.39 per sq ft only when the slab fails the test; 10% waste; and your crew's labor hours.
Every order includes a free 20-minute consultation to go over the slab and the kit count. Contractor pricing, drum pricing above 5,000 sq ft and the installer program are by phone at (877) 703-7699, Monday to Saturday, 8am to 6pm ET, or start at for installers and the kit builder.